Setting up profiles on site (Step by step)
- Set up first peg on site.
- Measure 7.2m with tape. (8.2m: Start 1m from tape for accuracy)
- Place peg two.
- Measure 15.5m from peg two. (16.5m)
- Place peg three.
- Measure 7.2m from peg three. (8.2m)
- Place peg four.
- Measure 15.5m from peg four to peg one. (16.5m)
- Place three pegs per corner.
- Measure 1m from pegs one, two etc...
- Form a three-point 90 degree angle with profiles.
- Set up dumpy
- Adjust bubble to center.
- Use 8m tape measuse to find mark 110mm for concrete level (FFL).
- From (FFL) 110mm mark, use tape measure.
- Find horizontal line via dumpy on tape measure.
- Use the same measurement for all profiles i.e (931mm).
- Mark the FFL
- Set up batter boards and bracing for profiles.
- Set up string line for the first two profiles.
- Square up all four profiles with string line.
- Use 3,4,5 technique to confirm measurements/squaring of site.
- Confirm measurements of 7.2m, 15.5m and diagonal 17.091m.
- Replace the four house site pegs to the final measurements from the string lines.
- Site is ready to be boxed for concrete.